A public inquiry into the £81 million redevelopment of Chelmsford’s Army and Navy junction opened on Tuesday 24 November 2026, as Essex County Council seeks approval for compulsory land purchases and road changes needed for the project.
The hearing at County Hall covers legal orders for the junction redesign and the expansion of Sandon Park and Ride.
Public inquiry begins at County Hall
The inquiry opened at 10am on Tuesday 24 November on the fourth floor of County Hall, Market Road, Chelmsford. Government-appointed inspector Stephen Normington is examining Essex County Council’s case and hearing objections.
The inquiry is expected to sit for four days, with additional dates reserved for Tuesday 1 December and Thursday 3 December.
The three orders under consideration concern compulsory purchase for the junction, compulsory purchase for Sandon Park and Ride, and changes to side roads around the junction. The inquiry is not a new planning application: the project received planning permission in November 2024.
What will change at the Army and Navy?
The existing five-arm roundabout would be replaced by a “hamburger” roundabout, with a road running through its centre. The wider scheme includes improved walking and cycling routes, an expansion of Sandon Park and Ride by approximately 350 spaces, a northbound bus lane on Princes Road and improved bus priority along Parkway.
Essex County Council says the package is intended to reduce congestion and improve options for public transport, walking and cycling.
Why is the junction being rebuilt?
According to Essex County Council, up to 75,000 vehicles use the junction daily, alongside 72 buses an hour. The council says journeys can take more than six times longer at peak periods.
The former tidal flyover closed permanently in 2019 because of structural safety concerns and was removed in 2020. Council modelling projects a 53% improvement in average private-vehicle journey times through the redesigned junction; this is a forecast, not an observed result.
Why is land acquisition being examined?
The council needs land and legal rights to deliver the junction changes and expand Sandon Park and Ride. Compulsory purchase orders can permit acquisition where voluntary agreements cannot be reached, subject to approval.
Issues raised in objections include land acquisition, environmental mitigation, proposed speed limits, effects on a business car park and land needed for Sandon Park and Ride. The inspector will consider evidence and report to the Secretary of State for Transport, who decides whether to confirm the orders.
How is the £81 million scheme funded?
The Department for Transport approved an outline business case in October 2023 and conditionally agreed £68.75 million through the Major Road Network programme. Essex County Council and Chelmsford City Council are contributing towards the balance. Final funding approval remains outstanding.
In March 2026 the council removed a proposed Chelmer Valley Park and Ride expansion from the current package following cost increases. The Sandon expansion remains part of the plans.
When could work start?
Essex County Council currently anticipates construction beginning in 2028 and completion of the overall package in 2031, subject to final funding approval and other agreements. The sequence of works has not yet been confirmed.
The inquiry itself does not mean construction or immediate changes to traffic arrangements are beginning.
What happens next?
After the hearings, the inspector will submit a report and recommendations to the Secretary of State for Transport. The Secretary of State will then decide whether the orders should be confirmed. No decision date has been announced.
Residents can read the inquiry papers and plans on the official Essex Highways project page.
Official documents: Essex Highways Army and Navy project and public inquiry.